Paving work at Lorenz Industrial Parkway and Commerce Court is complete. There are a few minor finish work items to complete over the next two weeks.
Paving is still planned for: Crocker Hill Road, Harvard Terrace, Oak Hills Trail, Van Tassel Drive, and Whalehead Road (section between Route 214 & Sandy Hollow Rd).
Work is presently anticipated to commence on Crocker Hill Road, Whalehead Road, and Oak Hills Trail, in this order, the week of September 19th. This phase should complete by the end of September, weather permitting.
The final phase of paving at Harvard Terrace and Van Tassel Drive should be completed by the end of October.